Gosnell Creek LWD and Fish Passage Project - Phase 2, Mason Conservation District, Shelton, WA #2026-03
$334,000
Plans
Specs
Job Show Sign In Sheet
Addendum #1
Register on this project.
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
Mason Conservation District
450 W Business Park Road
Shelton, WA 98584
accounting@masoncd.org
Contact: Andy Sorter
360-968-0736
asorter@masoncd.org
Issued by:
www.bxwa.com
Prebid: Mandatory: 3/24 @ 11:00 am, meeting at 251 W. Loertscher Road, Shelton, WA 98584
Notes:
Also incorporated into the Contract Documents by reference are:
•Manual on Uniform Traffic Control Devices for Streets and Highways, currently adopted 32 edition, with Washington State modifications, if any:
https://wsdot.wa.gov/engineering-standards/all-manuals-and-standards/manuals/manual-uniform-traffic-control-devices-mutcd
•Standard Plans for Road, Bridge and Municipal Construction, WSDOT/APWA, current 36 edition:
https://wsdot.wa.gov/engineering-standards/all-manuals-and-standards/standard-plans
•2024 Stormwater Management Manual for Western Washington (SWMMWW):
https://ecology.wa.gov/regulations-permits/guidance-technical-assistance/stormwater-permittee-guidance-resources/stormwater-manuals
•2019 Temporary Erosion and Sediment Control Manual, WSDOT:
https://www.wsdot.wa.gov/publications/manuals/fulltext/M3109/TESCM.pdf
Description:
MAJOR BID ITEMS will include: Mobilization, L.S.; Construction Work Plan, L.S.; Site Access & Staging, L.S.; Erosion Control and Water Pollution Prevention, L.S.; Temporary Stream Diversion, L.S.; Back Channel Excavation Including Haul and Spread, L.S.; Habitat/Complexity ELJ Construction, 9 EA.; Back Channel ELJ Construction, 1 EA.; Cleanup & Demobilization, L.S.; Key Log (Main Stem) (16”-18” x 15’) log with rootwad, delivered, 90 EA; Key Log (Back Channel) (16”- 18” x 12’) log with rootwad, delivered, 3 EA; Brace Log (16”-18” x 25’) log with rootwad, delivered, 9 EA; Timber Pile (12” x 20’), 54 EA; Slash (2”-4” dia. x <6’ length) delivered, 93 cubic yards (C.Y.); and Racking (4-8” dia. x <15’ length) delivered, 370 EA.